Six projects at once: what a new study says about project load
A construction consultancy asked project managers how often their jobs finish on time, then sorted the answers by how many jobs each manager was running. You can probably guess the shape of the result. The size of the gap is the interesting part.
On November 10, FMI, a consulting and investment banking firm that works with the construction industry, released the third and final part of its 2026 Project Management Study, titled "How the Role of Project Manager Is Evolving." It's based on responses from 243 construction executives and 84 project managers. Most of it is about how contractors define the job, train people for it, and what skills they think it'll need in five to ten years. One finding, though, travels well beyond job sites.
The number
Project managers with one to three active projects reported on-time or ahead-of-schedule performance 76% of the time. Managers with six or more active projects reported it 64% of the time.
Twelve points. That's roughly the difference between "usually fine" and "one in three things is late." Nobody gets assigned a sixth project with a memo saying "and also, your hit rate will drop." It just happens, a little at a time, and then everyone is in a meeting about why the Henderson job slipped.
What the study doesn't say
Before anyone prints this on a poster, some honest caveats. The figures are self-reported. The sample is construction, where a "project" might be a building, not a slide deck. And it's a correlation. It's entirely possible the people juggling six projects are handed the messier ones, or that the best managers get more work because they're the best managers, which is its own kind of reward.
FMI makes a version of this point itself. The report stresses that project count alone doesn't define capacity, and lists complexity, administrative work, support structure and process friction as things that also affect how much a manager can carry. That's fair. Three tangled projects can weigh more than six tidy ones.
Still, the direction matches pretty much everything else we know about divided attention. Each extra project isn't just more work. It's another set of people to update, another schedule to hold in your head, another place for something to go quiet without you noticing. We've written before about the cost of context switching, and a project is about the largest context there is.
Why the count matters even if you don't build things
Most knowledge workers have never been asked how many projects they're running. They'd have to stop and count, which tells you something. Client work, an internal initiative, the hiring loop, the thing your manager mentioned once in June and still brings up. Each of those has its own deadlines, its own people, and its own pile of things you're waiting on.
The FMI finding is really an argument for making the count visible. Not because there's a magic number, but because you can't negotiate a load you can't see. "I'm busy" is easy to wave away. "I'm running seven projects and four of them are blocked on other people" is a sentence that tends to change the conversation.
This is the same idea as personal WIP limits, one level up. WIP limits cap how many actions you have in flight. A project limit caps how many separate streams of actions you're trying to keep moving. And if you like your intuitions backed by arithmetic, Little's law explains why piling more in tends to make each thing take longer rather than making more things finish.
The other part: who has the ball
One more detail from the report deserves a mention. 85% of executives identified the project manager as the primary customer contact. In other words, the role isn't just doing the work. It's also being the person everyone calls to ask where the work is. Multiply that by six projects and a good chunk of the day goes to answering status questions instead of moving anything.
That's where a lot of the slippage hides. A project rarely goes late because the manager forgot it existed. It goes late because something sat with a subcontractor, a client, or a colleague for two weeks and nobody chased it. With three projects, you'll probably notice. With six, the quiet ones are exactly the ones that get missed. This is the waiting-on-someone problem at scale.
What to do with it
You probably can't hand back three projects tomorrow. Few people can. But there are a few things that help regardless.
Count them. Write down every active project, including the ones you'd rather not admit are projects. If the number surprises you, that's information.
Split each one by who has the ball. For every project, what's on you, what's waiting on someone else, and what's next. A project where everything is in someone else's court isn't idle, it needs a nudge. A project where everything is on you is where your week actually goes.
Use the count when you're offered more. "Happy to take it on. Which of these should slow down?" is a reasonable response, and it's much easier to say with a list in hand.
A small confession
The free version of Axtio caps you at three projects. We'd love to claim we read this study and designed around it, but the limit predates the report and was mostly about keeping a free tier sensible. Still, it's a nice coincidence that three sits right at the top of FMI's best-performing band. One board with a row per project and columns for who has the ball makes the count impossible to ignore, which is the point. If your work looks like a job site, our guide to Kanban for construction project managers goes into more detail.
The study won't tell you your number. It does make a decent case that the number exists, and that it's smaller than whatever you're carrying right now.
Sources
FMI Corporation, "FMI Releases Final Installment of 2026 Project Management Study", November 10, 2026. All figures (243 executives, 84 project managers, 76% versus 64% on-time performance by project load, 85% naming the project manager as primary customer contact) come from that release. The full report, "How the Role of Project Manager Is Evolving," is available from FMI. Accurate as of November 2026.